Packaged Chiller Service

Brazing equipment box and vibration eliminators during packaged chiller service

Packaged Chiller Service

Packaged chiller service due to a refrigerant leak, resulting in a trip out. This visit was to identify the leak and get the plant back online.

Leak Testing During Packaged Chiller Service

Nitrogen was added to the system to aid in the identification of the leak. All parts of the system were checked, including the removal of lagging around the couplings onto the evaporator. The leak was found on a poor quality ‘eliminator’ which had rubbed through on the evaporator.

Vibration Eliminators

We decided to fit high quality vibration eliminators- see picture. These are fitted one in the horizontal position and the other in the vertical. They absorb both directions of vibration then they are clamped to the chiller frame.

Brazing During Packaged Chiller Service

The pipework brazing was carried out during packaged chiller service with all combustible materials being removed from the work location. A permit to work was opened with our engineer as the responsible person. A half hour fire watch was carried out on completion of works.

0161 370 7193

service@maximuschillers.com

Contact Form

Pressure Test During Packaged Chiller Service

The pressure testing was carried out using nitrogen. As nitrogen is an inert gas, it will not cause other potential risks to the chiller and other personnel. The pressure test was a pass, so the next phase of the job could be carried out…

Vacuum Pump

Each engineer carries a 10 cfm vacuum pump. This high capacity ensures a fast vacuum. The Torr gauge was fitted to the system and 2 Torr was pulled.

Refrigerant Saturation

In the cylinder, the saturation of R407c is 7 bar at 11° The refrigerant in the cylinder is in its liquid phase with vapour on top.

Subcooling

On run testing the chiller, the subcooling value was found to be nominal at industry standard level.

Superheat

The superheat was adjusted, little by little, with the charging of the refrigerant until a good value was achieved. This was tested across all loading conditions for the rest of the visit.

Related Articles:
Chilling Plant Service

Global Chilled Water System Service

Chilled Water System EEV Service

Water System Service of Evaporator

Chiller Service of Fan Decks

HFC Chiller Service

Process Chiller Vacuum Service

Read more about reducing refrigerant leaks at the Institute of Refrigeration | Click Here


Engineer carrying out process chiller service with yellow and black cylinder

Process Chiller Service

Maximus Chillers has just carried out process chiller service to a flooded evaporator. The refrigerant seal on a four bolt, flanged coupling had been found to be leaking liquid refrigerant. There was no possibility to valve off that section of the machine, as the flooded evaporator is the storage vessel for all of the charge of the system in its liquid phase.

Refrigerant Decant for Process Chiller Service

Our high capacity pump out unit was set up next to the machine to carry out process chiller service. 55 kg of refrigerant was recovered in a short time into our recovery cylinder. This refrigerant was collected for recycling after the job was completed.

Process Chiller Refrigerant Leak Service

The flanged coupling was unbolted and the failed refrigerant seal was removed. The new seal was fitted from our full range of sizes that we keep on the shelf in our stores. Our engineer bolted the flanged coupling back up to the correct torque setting.

Pressure Leak Test

A nitrogen pressure leak test was carried out to ensure the integrity of the system with the result being a pass.

Dehydration Process

As the system was open to atmosphere, air had got into the system which carries moisture content. The moisture and non condensables were removed down to a near perfect vacuum using one of our high capacity vacuum pumps.

0161 370 7193

service@maximuschillers.com

Contact Form

Charging of Refrigerant

The photo shows the charging of a cylinder of refrigerant into the system in its liquid phase. The cylinder has a dip tube fitted for ease of cylinder handling. Once the pressure in the system and the cylinder equalized, remaining refrigerant was drawn into the system during the operation of the plant.

Run Testing

The sight glasses and level glasses were found to be at the optimum level under the normal running conditions of the process chiller. As it is a flooded system, there was found to be a low superheat value. A high subcooling value was achieved with the use of a subcooler. Our engineer monitored a full cycle of an hour and a half: compressor temperatures and oil level were found to be within normal operating limits.

Remote Service Monitoring of Process Chiller

The service of this process chiller can be remotely monitored via a data uplink through the internet. Our office continued to monitor the plant for some days as it went into seamless operation.

Related Articles:
Chilling Plant Service

Global Chilled Water System Service

Chilled Water System EEV Service

Water System Service of Evaporator

Chiller Service of Fan Decks

HFC Chiller Service

Process Chiller Vacuum Service

Follow this link to purchase BESA pressure testing technical bulletin Click Here


Chilling plant service showing yellow top recovery cylinder with gauge line and sight glass fitted

Chilling Plant Service

Our customer had been having high pressure service problems on his chilling plant.

Transducer Required Chilling Plant Service

The 4-20mA transducer needed service on the chilling plant. It was reading low by a long shot. Therefore, the PLC was not bringing the fans on as it should. The pressure in the high side of the system was getting up to 40 bar. This is because the refrigerant was R410a- it has a higher head pressure than other commonly used HFC refrigerants, such as, R407c. We ordered the replacement transducer which is fitted with a female fitting.

Chilling Plant Service Leaks

He concentrated his attention on the high side of the system to start with. Then, found a leak on a fitting, a leak on the pressure relief valve fitting and a leak on the liquid line near the drier. A sealant was used for leaks on the fittings- they were removed, cleaned and refitted. The leak on the liquid line was re sealed by removing the section of pipe, removing any remaining solder then the section of pipe was re made.

0161 370 7193

service@maximuschillers.com

Contact Form

Pressure Test

The remaining parts of the system were leak tested then the chilling plant was put on a pressure test to ensure the whole system was leak free. The pressure test was satisfactory and so the evacuation process could be started.

Evacuation Process 

Each of our engineers has a powerful vac pump to speed up the dehydration process on the chilling plant being serviced. This means that a deep vacuum can often be pulled on the same day instead of the usual overnight process. The nitrogen and other non condensables were removed quickly and the Torr gauge came down to the pressure where moisture was being removed. At this pressure, any moisture is forced to boil off around the system.

Recharging of the Chilling Plant Being Serviced

In the photo, the chilling plant is being recharged at the end of the service work. It is being recharged into the liquid side of the evaporator. All readings were okay when running the system and further leak tests were carried out at normal operating pressures.

Related Articles:
Global Chilled Water System Service

Chilled Water System EEV Service

Water System Service of Evaporator

Chiller Service of Fan Decks

Process Chiller Service

HFC Chiller service

Process Chiller Vacuum Service

Read more about refrigerant reclamation by following this link to Wikipedia | Click Here


A chiller condenser retrofitting lifting operation outside in the compound

R407c Chiller Condenser Retrofitting

We recently undertook the job to carry out bespoke R407c chiller condenser retrofitting in the North West.

Rusted and Corroded Condenser

The old condenser looked alright on the surface- the fins were in good condition. The chiller condenser was 18 years old and when an attempt to repair a leak was carried out- the condenser leaked further along. This is because of the warming of rusted and corroded copper with an oxy-acetylene torch.

R407c Chiller 'V' Condenser Retrofitting

We arrived on site to measure up for the job. The ‘V’ chiller condenser being retrofitted was built to order. We manufactured an exact replica to the same specifications and sizes of the old one. The operating pressures and high pressure cut out limit were taken into account in the design and the use of materials.

0161 370 7193

service@maximuschillers.com

Contact Form

Lift Out of the R407c Chiller Condenser being Retrofitted

On the day of the lift and shift we isolated the panel and checked it was dead, then we removed the panel and laid it on it’s front. This was to access the rivets behind the panel. These rivets, the ones on the other end of the chiller and around the lid were removed using a tool. The fans were disconnected and removed to make the lid lighter to lift off. Then, we attached slings to the chiller condenser and lifted both halves of the 'V' out.

Lift In of the Chiller Condenser being Retrofitted

This part we did not want to get wrong as the R407c chiller condenser being retrofitted was brand new and did not have a mark on it. A reverse of the removal- it fitted perfectly just the same as the old one. With the lid lifted back on and the fans in- time for brazing then the pressure test.

Pressure Test, Dehydration and Recharge

The pressure test was satisfactory so our engineer put the system on vac for dehydration purposes and the removal of non condensables. After a deep vacuum was achieved the system was recharged and run tested. No issues were found.

Related Articles:
Chiller Refurbishment Supplier

Chiller Refurbishment Company

Chiller Parts Supplier

Read more about air cooled condensers at the Institute of Refrigeration | Click Here


Translate