Chiller Condensers

Boxed, shell and tube chiller condenser being lifted into a building with a crane

Chiller Condensers

Shell & Tube

The chiller condenser on a 2 MW centrif we look after had deteriorated over a long period of time. We had carried out tube cleaning and noticed that it had been extensively repaired in the past. There were a lot of damaged tubes that had been blanked off. This had reduced the useful surface area for heat exchange to occur. The chiller was experiencing a ‘discharge limiting’ condition which was causing it to back off to 54% capacity.

Air Cooled

Because of the difficulty to remove and replace the condenser from the plant room, the customer had explored the possibility of air cooled condensers. His idea was to fit the discharge and liquid piping up the side of the building and into the plant room. After considering this possibility, we decided to advise him against using air cooled condensers because it would take two, 16 fan ‘V’ types. This would have a footprint too big for the available space. We decided to use a crane to lift out the old condenser, then lift in the new one.

Pump Out

The old condenser was valved off from the rest of the system and the refrigerant was pumped into an 800 kg recovery vessel. This was one of 2 vessels in the plant room that had been there since the chiller was new.

0161 370 7193

service@maximuschillers.com

Contact Form

Lift Out for Chiller Condensers

The pipework was unbolted and the ancillaries removed. When it came to unbolting the condenser, some of the bolts were seized due to a long period of rusting. Some of them came loose by heating them with oxy-acetylene, the others were ground off with an angle grinder. We used a specialist lifting company to shift the condenser from the plant room and out to the lifting bay. They then attached slings to one end, manoeuvred that end of the condenser to the outside of the building, then attached slings to the other end. Rather them than me! Quite a dangerous operation, but it had been assessed when composing their Risk Assessment Method Statement. The condenser was lifted onto the back of an articulated truck and taken to a scrap yard for recycling. There was quite a lot of copper inside- so our customer got quite a good weigh in!

Lift In for Chiller Condensers

The new condenser, in the photo, was kept in its packaging during the lift up, so as to protect it from damage. Once it was in the building and near to the plant room, it was removed from the box and shifted the rest of the way with dollies. There was some difficulty getting it into its final location. This was because the old steelwork had to be cut back with a blow torch to make the new condenser fit. Also, with limited room and no gantry crane, the lifting company had their work cut out to manoeuvre it. Eventually, it was in location and we decided to call it a day.

Adapting the Pipework

This particular condenser was selected because it was similar in dimensions to the old one. The positioning of the refrigerant and water system pipework was similar too. That said, it was not an exact match. We called an industrial plumbing and welding company in to make the changes we needed. They measured up and built adaptors to bolt in between the condenser and the water system pipework. They cut back the new condenser discharge connection and welded a new flange on. This was so it could be bolted onto the existing discharge elbow from the chiller. The liquid pipe connection on the new condenser was in the same location, but came with a different thread. Therefore, this too was cut back and an adaptor fitting was welded into place.

0161 370 7193

service@maximuschillers.com

Contact Form

Ancillaries

The fittings on the new condenser were BSP and the fittings on the chiller were Flare. We carry an extensive range of fittings that go between BSP and Flare. We can go from male to female, female to male, male to male and female to female. We can step up and step down in size too. Using these fittings, we attached the high pressure switch and high pressure transducer. The wires for the liquid and discharge temperature sensors were extended. This was so they could reach the location of the pockets that were built into the new condenser. Then, we used a special heat transfer paste to get a good transmission of heat in between the sensors and the pockets.

F-gas Pressure Test

We then carried out a strength test and a pressure test in accordance with F-gas guidelines. This was witnessed at the beginning and at the end by the customer. A satisfactory outcome was achieved, so on to the next phase of the job…

Dehydration of Chiller Condensers

We needed to dehydrate the system and remove the nitrogen that was used in the pressure test. This is because nitrogen is a non condensable which will affect system performance. Our powerful vacuum pump was set up, then we left it running overnight. A 1.5 Torr vacuum was achieved, which was the same pressure as when the Torr gauge was fitted directly on to the vacuum pump.

Open the Valves and Test

After removing the vacuum pump, the recovered refrigerant was pumped back in, then the discharge and liquid valves were opened back up. Then, our engineer had a good look round for leaks. I know it had just been pressure tested, but we think it’s always a good idea to check again. This done, the water system pumps were started and the water temperature showed at 23°C on the controller. The set point for the chilled water was 6°C so this warm water was helpful as it gave us plenty of load to carry out the testing. The chiller went through a timer and then started up. It loaded steadily up to 100% with no dramatics- splendid!

Related Articles:
Chiller Parts Supplier

Chiller Compressors

Air Cooled Chiller Condenser Maintenance

Shell & Tube Evaporator Maintenance

Screw Chiller Compressor Maintenance

Chiller Controls

Scroll Chiller Compressor Maintenance

Centrifugal Chiller Compressor Maintenance

Reciprocating Chiller Compressor Maintenance

Chiller Controls Company

To read more about chiller condenser systems hit the Tag at the top of the page.

Read more about chiller condensers on The Engineering Mindset | Click Here


Large chiller, refrigerant cylinder, brazing equipment and tools during chiller service company visit

Chiller Service Company Visit

A typical rainy day in the North West, perfect for a chiller service company visit.

News Article No.11

Electrical Faults during Chiller Service Company Visit

This was a return visit to do a refrigerant leak, but the customer alerted our engineer’s attention to an electrical fault. System 2 was found to be locked out in fault on the recent maintenance visit, but now System 1 was being held off too. The fault message on the controller was High Pressure. The controller sends a 240v fault feedback signal, through the high pressure switch which returns to the controller. Our engineer had a look at the wiring diagram to find the number on the terminal strip and checked it out with his multimeter. As he suspected, there were volts going out, but not coming back. He removed the side panel for system 1 and found the switch on the discharge pipe. It was the type that has a red button on the top. When he pressed it, there was a click and volts returned to the controller.

Alarm Reset during Chiller Company Service Visit

He interrogated the Carel controller and followed the reset procedure. The controls went through a timer and then the start sequence was initiated.

Run Testing during Chiller Company Service Visit

After the first scroll compressor started, the head pressure started to build up, but the condenser fans did not start. The on board high pressure gauge carried on rising until the high pressure switch was tripped again.

Head Pressure Control

A transducer on the discharge is used by the controller to sense the pressure in the condenser. When our engineer looked for this in the controller, it was found to be reading wrong by a considerable amount. There is a facility to enter a password and recalibrate the transducer, but this only allows for a small adjustment.

Test Instrument

Our engineers carry various kinds of test instruments which can be used to give a temporary false reading to the controller. This gets the customer up and running and back in production whilst a new transducer is ordered and sent to site.

0161 370 7193

service@maximuschillers.com

Contact Form

Chiller Company Service Low Pressure Visit

Now on with the job to resolve the low pressure issue with the chiller.

Refrigerant Pump Out

Our engineer lifted the liquid line solenoid valve and decanted the remaining refrigerant into a vessel using his recovery unit. He only got out 7kg of a charge of 36kg.

Leak Testing during Chiller Company Service Visit

We use nitrogen for the leak testing as it is an inert gas that will not cause problems with the refrigerant system. There was a sign of the leak in between the steel frame at the middle of the condenser and the condenser tubes. We always strip the chiller down and leak test the entire system though. This is so that the job does not end up going round in circles. At first the leak could not be found, so the pressure was built up in stages, taking into account industry recommended guidelines for a chiller. Sure enough the leak was where it was suspected to be. The occurrence of this kind of leak can be reduced with the use of vibration eliminators.

Brazing during Chiller Company Service Visit

The location of the leak was reported to the maintenance engineer onsite and a hot work permit obtained. The equipment we use is tested at regular intervals to be safe and in good working order. A half hour fire watch was stipulated in the permit, along with the removal of combustible materials from the work location. Correct PPE being donned, he brazed the leak to the required industry standards.

F-gas Pressure Test

A chiller has a different pressure test procedure to other systems, so our engineer built the pressure up according to industry standards, then recorded it on his pressure test certificate. After the required time had elapsed, he rechecked the readings which were found to be satisfactory.

Vac Pump

Each of our engineers carries a state of the art 10 cfm vacuum pump to speed up the dehydration process. We use high quality Torr gauges too, so as to get an accurate pressure reading. A good read back was achieved at the end of the process.

Recharge and Run Test

After the refrigerant recharge was carried out, a satisfactory run test was achieved.

0161 370 7193

service@maximuschillers.com

Contact Form

Refrigerant Economizers

This particular chiller uses an economizer to further subcool the refrigerant. Chiller designers have worked out that the end user can save a considerable amount of money over 10 years if these components are used. After the subcooled liquid refrigerant leaves the condenser, it goes through a plate heat exchanger. Some of this refrigerant, however, is diverted through a thermostatic expansion valve, to the other side of this plate heat exchanger. Further subcooling occurring through the plates.

Expansion Valve

The refrigerant drops in pressure as it goes through the expansion valve. A bulb is fitted to the suction pipe on the outlet of the heat exchanger. The bulb has to be at the correct 'o clock position as oil insulation will affect the operation of the valve. A capillary tube connects the bulb to the valve. Inside the bulb, the same kind of refrigerant that is running in the system is present in its liquid state. As the temperature rises in the suction pipe, this refrigerant boils off, adding pressure into the capillary tube. This added pressure forces the power element down on the valve body and a needle forces the valve open.

Flash Gas

Imagine if the refrigerant was not subcooled at all. It would be around its saturation point with a lot of it flashing off into its vapour phase. Not good when you have warm water coming back from the process. The refrigerant would not absorb very much latent heat into the refrigerant system.

Efficiency

Imagine, on the other hand, the economizer which is fitted to this chiller. Now we have a good proportion of refrigerant in its liquid phase, on the low side of the system, with a minimum amount of flash gas. The warm process water has more chance to cool and the refrigerant absorbs a lot more latent heat. The chiller achieves set point easier and therefore saves a considerable amount of electricity. With this further subcooling monitored for a while, time for a signature from the customer and another job well done!

Related Articles:
Chilling Plant Service

Chilled Water System EEV Service

Water System Service of Evaporator

HFC Chiller Service

Process Chiller Vacuum Service

Chiller Breakdown

Chiller Fault Finding & Diagnosis

F-gas Chiller Leak Testing

Chiller Commissioning

To read more about chiller electrical faults hit the Tag at the top of the page.

Read more about F-gas leak checking at Refcom | Click Here


An R407c chiller condenser retrofit lifting operation outside in the compound

R407c Chiller Condenser Retrofitting

We recently undertook the job to carry out bespoke R407c chiller condenser retrofitting in the North West.

Rusted and Corroded Condenser

The old condenser looked alright on the surface- the fins were in good condition. The condenser was 18 years old, however, so when an attempt to repair a leak was carried out- the condenser leaked further along. This is because of the warming of rusted and corroded copper with an oxy-acetylene torch.

R407c Chiller 'V' Condenser Retrofitting

We arrived on site to measure up for the job. The ‘V’ condenser was built to order. We manufactured an exact replica to the same specifications and sizes of the old one. The operating pressures and high pressure cut out limit were taken into account in the design and the use of materials.

0161 370 7193

service@maximuschillers.com

Contact Form

Lift Out of the R407c Chiller Condenser being Retrofitted

On the day of the lift and shift we isolated the panel and checked it was dead, then we removed the panel and laid it on its front. This was to access the rivets behind the panel. These rivets, the ones on the other end of the chiller and around the lid were removed using a tool. The fans were disconnected and removed to make the lid lighter to lift off. Then, we attached slings to the chiller condenser and lifted both halves of the 'V' out.

Lift In

This part we did not want to get wrong as the condenser was brand new and did not have a mark on it. A reverse of the removal- it fitted perfectly just the same as the old one. With the lid lifted back on and the fans in- time for brazing then the pressure test.

Pressure Test, Dehydration and Recharge

The pressure test was satisfactory so our engineer put the system on vac for dehydration purposes and the removal of non condensables. After a deep vacuum was achieved the system was recharged and run tested. No issues were found.

Related Articles:
Chiller Refurbishment Supplier

Chiller Refurbishment Company

Read more about air cooled condensers at the Institute of Refrigeration | Click Here


Chiller service of fan decks showing 8 fans

Chiller Fan Deck Service

Bodger Watch

Chiller fan deck service is usually very good, but this is bodger watch! A new customer of ours was telling us about this little guy that used to come. He was reported to have been running around like the apprentice- ringing everybody up! Then when help came, it came in the form of this huge, big man who proceeded to get stuck in the chiller! You couldn't make it up! This is bodger watch! The customer asked for a professional service from Maximus Chillers.

Repeated Leaks on Condenser

Our engineer found the head pressure control was bringing the fans thumping on and off forwards and backwards. During a visit, the fans were found to be rattling the frame and juddering the chiller into leaks.

0161 370 7193

service@maximuschillers.com

Contact Form

Learning How to Think

Instead of just swapping like for like parts. Our engineers have the capability to think outside the box and make changes to chiller design. All of our engineers attend the Maximus School of Chillers at Head Office in Droylsden, Manchester. Read More on the Chiller Company page.

Fan Speed Controller during Chiller Fan Deck Service

On a return visit, we fitted off the shelf fan speed controllers from our stores- one for each system. These fan speed controllers are stand alone- they do not need to be integrated into the existing controls. When the pressure builds up- the fan speed controller speeds the fans up from the minimum (cut in) to the maximum (same volts as the incoming supply)

Chiller Fan Deck Service for Seamless Operation

Now the fan speed controllers are fitted- there are no more leaks. Any chiller can be made to settle down into seamless operation.

Are you a factory manager or facilities manager with recurring leaks on your chillers? Need your fans replacing or the controls adjusting? Look no further than Maximus Chillers.

Related Articles:
Chilling Plant Service

Chilled Water System EEV Service

Water System Service of Evaporator

HFC Chiller Service

Process Chiller Vacuum Service

Chiller Service Company

Chiller Breakdown

Industrial Chiller Service

Chiller Service Company Visit

Chiller Fault Finding & Diagnosis

Visit the Institute of Refrigeration to read a paper on the comparison between air cooled condensers and evaporative condensers.


Translate