On a recent visit to Saudi, our overseas chiller engineer carried out an evaporator repair. This customer flew us out because of on going issues with their evaporators. Various recommendations were made to improve reliability….

Water Treatment

A full analysis of the chilled water quality was carried out including samples being sent to our laboratory at Head Office.

Bacterial Growth

There had been a bacteria problem which had occurred 4 years ago. The water temperature and conditions can be just right for a particular type of bacteria to thrive. The bacterial growth spreads around the water system, the plate heat exchangers and the evaporators until it completely coats all surfaces.

Thermal Insulation

This bacterial layer can be 2mm thick and acts as insulation between the heat exchanging water and refrigerant. This dramatically reduces the capacity of the chillers. The chillers achieve set point due to not sensing heat. The factory gets warmer due to not being able to reject heat.

Saudi Chiller Evaporator Repair using Biocide

The customer had brought in a chemical treatment company who started using a biocide to control the bacteria. This had worked effectively, but it had a knock on effect…

Corrosion

The evaporator tubes had been corroded away with the over use of the biocide. When our overseas engineer inspected the MSDS (Material Safety Data Sheet) for this particular chemical, he found it to be corrosive. When he analysed the dosing rate, he found that it had been significantly over dosed. This over dosing had corroded and rotted through the copper evaporator tubes which was causing re occurring refrigerant to water leaks.

Solution

The solution was to recommend a full drain down of the water system when the factory was in shut down. A list was provided to the customer detailing which chemicals should be used and their dosage. This list included a biocide, an inhibitor, PH control chemicals and chloride control chemicals.

0161 237 3727

service@maximuschillers.com

Contact Form

Water System Components

The water system components were found to be installed in the wrong position, or not installed at all. This was found to be another major contributing factor to the frequent evaporator failures. A previous design company had sent our customer the plans of how to build the water system, but these plans had been mis interpreted by the local industrial pipework company.

Incorrect Flow Rate

The onsite chiller engineer has all of the necessary charts and tables along with the design specifications supplied by the evaporator manufacturer. However, because of the above, he had found it impossible to regulate the correct flow rate through the evaporators. This incorrect flow rate had caused various evaporators to weaken and then burst.

Strainer

Most of the evaporators were found to be in use without a strainer fitted. This meant that foreign objects from around the water system were rattling through the evaporators and then causing damage.

Re Installation

After a report was forwarded to the onsite repair manager, a local consultant was brought in to oversee the re installation of the chiller pipework. Each chiller’s water system pipework was scheduled to be repaired one at a time, this was so that minimal disruption was caused to the factory process.

Test Points for Saudi Chiller Evaporator Repair

Pressure and temperature gauges were fitted at the same time that the chiller pipework was re installed. This was to allow the onsite chiller engineer to carry out the necessary adjustments to the water system flow rates.

Rebuild during Saudi Chiller Evaporator Repair

The photo shows one of the chiller evaporators with the end plate removed during repairs. The onsite chiller technician in the photo was carrying out an inspection to the tubes to identify which ones were leaking.

Tube Repairs

The leaking tubes were then taken out of use. Standard industry guidelines were used to pressure test the rest of the evaporator to ensure the integrity of the system.

0161 237 3727

service@maximuschillers.com

Contact Form

Dehydration Process during Saudi Chiller Evaporator Repair

Next, the water that had got into the refrigerant system needed to be removed. This was a difficult process as the compressor had sucked the water through and discharged it into the condenser. Luckily, the amount of water going through the compressor had not damaged it. This was because the compressor is a high quality Bitzer which is very robust. The vacuum pump was fitted to the system and the moisture removal process was carried out over a period of weeks.

Refrigerant Recharge

Having successfully carried out the dehydration process, the refrigerant system was charged with R407c refrigerant. The refrigerant quantity on the data plate was used a guideline. However, system sanding pressure was achieved as the pressure equalised between the refrigerant cylinder and the refrigerant system.

Low Pressure Trips during Saudi Chiller Evaporator Repair

The chiller was started up and then tripped on low pressure shortly afterwards. This was because there was still a shortage of refrigerant in the system. Therefore, more liquid refrigerant was charged into the system until the chiller ran without tripping out.

Superheat and Subcooling

The superheat and subcooling values were found to be outside standard industry guidelines. Therefore, refrigerant was continued to be charged into the system under full load conditions. The onsite chiller technician continually monitored the readings on his test equipment and the program readings of the chiller. After an hour of trimming the refrigerant charge and monitoring the readings, he got the superheat and subcooling values to be within standard industry guidelines.

Related Articles:
Shell & Tube Chiller Evaporator Maintenance

Water Chiller Service of Evaporator

Hit the Tags below to navigate your way to our extensive library of further reading on this subject.

Read more about why a chilled water system needs treatment on Kimpton Energy Solutions.

Translate